Script: CrtItem -
Define a Discrete Item
Login:
mfg/welcome
Task:
Define a Discrete Item
Actions:
1. Navigate: Inventory/Items/Master Items
2. Select Organization=M1, Seattle
Manufacturing
(NOTE:
Specific Items used in this test refer to Vision seeded data.)
3. Enter information in master Item form:
Key in Item: ITEMTEST1
(Note:
Every Item should be unique)
Description:
Discrete Test Item
4. Enter data to the following Tab
Regions: Main Tab Region:
Pri
UOM: Each
User
item type: Finished Good
Item
Status: Active Inventory Tab Region: Inventory Item: Check Stockable: Check
Reservable: Check Transactable: Check Lot - Control: No Control Serial
Generation: No Control Locator control: No Control
Bills
of Material Tab Region: BOM Allowed: Check BOM Item Type: Standard Effectivity
control: Date
5. Enter data for: Costing Tab Region:
Costing Enabled: Check Inventory Asset Value: Check Include in Rollup: Check
Cost
of Goods Sold Account: (default)
Standard
Lot Size: 1
Purchasing
Tab Region: Purchased: Check Purchasable: Check
Allow
Description Update: Check
RFQ
Required: NO
Taxable:
No
List
Price: 1500
Price
Tolerance: 0
Expense
Account: (default)
Market
Price: 1500
6. Enter data for Receiving Tab Region:
Allow
Express Transactions: Yes
Receipt
Routing: Direct
7. Enter data for:
General
Planning Tab Region: Inventory Planning Method: Not Planned Make or Buy: Make
Cost:
Carrying: 10%
Safety
Stock: Method: MRP Planned %
Safety
Stock: Percent: 15
MPS/MRP
PlanningTab Region: Planning Method: MPS planning Forecast Control: Consume and
Derive MPS Planning: Calculate ATP: Check MPS Planning: Reduce MPS:None
Planning Time Fence: User-Defined, Days: 8 Demand Time Fence: User-Defined,
Days: 3
8. Enter data for:
Lead
Times Tab Region: Preprocessing: 2 Fixed: 1
Variable:
.01
Lead
Time Lot Size:1
Work
In Process Tab Region: Build in WIP: checkbox Supply Type: Push
Order
Management Tab Region: Customer Ordered: Check Internal Ordered: Check Customer
Orders Enabled: Check Internal Orders Enabled: Check Shippable: Check
OE
Transactable: Check
Returnable:
Check
Default
Shipping Organization: (default, else M1, Seattle Manufacturing)
9. Enter data for: Invoicing Tab Region:
Invoiceable Item: Check Invoice Enabled: Check Sales Account: (default) Service
Tab Region:
10. Click on Service tab.
11. Select File/Save (stay in form for next
step)
12. Select Tools/Organization Assignment from
the Menu bar. (115inv056.gif)
13. Click Assigned check box for M1, Seattle
Manufacturing and M2 Boston Manufacturing.
14. Select File/Save.
15. Close Organization Assignment form by
using the “x” box
16. Change ITEMTEST1, item Attribute Region:
Work In Process Tab Region:
Supply
Type: Operation Pull
17. Select File/Save (stay in form for next
step)
18. Change ITEMTEST1, item attribute: Work In
Process Tab Region: Supply Type: Push
19. Select File/Save.
20. Close Master items form by pressing F4
key
Verifications:
1. Master Item form is displayed when
Navigate: Inventory/Items/Master Items.
2. Main Tab Region is displayed when enter
data to the Tab Regions.
3. Inventory Tab Region is displayed when
enter data to the Tab Regions.
4. Bills of Material Tab Region is
displayed when enter data to the Tab Regions.
5. Costing Tab Region is displayed when
enter data to the Tab Regions.
6. Purchasing Tab Region is displayed when
enter data to the Tab Regions.
7. Receiving Tab Region is displayed when
enter data to the Tab Regions.
8. General Planning Tab Region is
displayed when enter data to the Tab Regions.
9. MPS/MRP Planning Tab Region is
displayed when enter data to the Tab Regions.
10. Lead Times Tab Region is displayed when
enter data to the Tab Regions.
11. Work in Progress Tab Region is displayed
when enter data to the Tab Regions.
12. Order Entry Tab Region is displayed when
enter data to the Tab Regions.
13. Invoicing Tab Region is displayed when
enter data to the Tab Regions.
14. Service Tab Region is displayed when
enter data to the Tab Regions.
15. Organization Assignment form is displayed
when select Tools/Organization Assignment.
16. Organization Assignment form closes and
focus returns to Master Items form when Close using the “x”.
17. Work In Process Tab Region is displayed
when enter data to the Tab Regions.
18. Work In Process Tab Region is displayed
when enter data to the Tab Regions.
19. Master Items form closes and focus
returns to Navigator.
Responsibility:
Manufacturing & Distribution Manager Organization=M1, Seattle Manufacturing
(NOTE:
Specific Items used in this test refer to Vision seeded data.)
Task:
Define a discrete item
Actions:
1. Navigate: Inventory/Items/Master Items
2. Click Tools/Copy From Item: CM13139
3. Click Apply
4. Click Done
Key
in Item:ITEMTEST2
(Note:
Every Item should be unique)
Description:
Discrete Test Item
5. Verify Inventory Tab Region: Inventory:
Check Stockable: Check Reservable: Check Transactable: Check
Lot
Control: No Control
Serial
Generation: No Control
Locator
Control: No Control
6. Verify MPS/MRP Planning Tab Region:
Planning Method: MRP planning Forecast Control: None
Pegging:
None
Planning
Time Fence: User-Define
Days:
1
7. Verify Work In Process Tab Region:
Build in WIP: Check
Supply
Type: Operation Pull
8. Modify Order Management Tab Region:
Check ATP: None
ATP
Components: None
9. Select File/Save (stay in form for next
step)
10. Select Tools/Organization Assignment from
the Menu Bar.
11. Click Assigned check box for: M1, Seattle
Manufacturing M2, Boston Manufacturing
12. Select File/Save from the Organization
Assignment form.
13. Close Master items form by pressing F4
key.
Verifications:
1. Master Item form is displayed when
Navigate: Inventory/Items/Master Items.
2. Main Tab Region is displayed when enter
data to the Tab Regions.
3. Inventory Tab Region is displayed when
enter data to the Tab Regions.
4. MPS/MRP Tab Region is displayed when
enter data to the Tab Regions.
5. Work In Process Tab Region is displayed
when enter data to the Tab Regions.
6. Order Management Tab Region is
displayed when enter data to the Tab Regions.
7. Enable new item in M1, M2 when click
Assigned check box.
8. Organization Assignment form is
displayed when Select File/Save.
9. All of Master Items forms close and
focus returns to Navigator when press F4.
Responsibility:
Manufacturing & Distribution Manager Organization=M1, Seattle Manufacturing
(NOTE:
Specific Items used in this test refer to Vision seeded data.)
Task:
Define a discrete item
Actions:
1. Navigate: Inventory/Items/Master Items
2. Select Tools/Copy From Item: CM13139
3. Click Apply.
4. Press Done.
5. Key in Item: ITEMTEST3
Description:
Discrete Test Item
6. Verify Inventory Tab Region: Inventory
Item: Check Stockable: Check Reservable: Check Transactable: Check
Lot
- Control: No
Serial
- Generation: No Control
Locator
Control: No Control
7. Verify MPS/MRP Tab Region: Planning
Method: MRP Planning
Forecast
Control: None
Pegging:
None
Round
Order Quantities: Check
Planning
Time Fence: User-Define
Days:
1
8. Verify Work In Process Tab Region:
Build in WIP: Check
Supply
- type: Operation Pull
9. Modify Order Management Tab Region:
Check ATP: None
ATP
Components: None
10. Select File/Save (stay in form for next
step)
11. Select Tools/Organization Assignment.
12. Click Assigned check box for: M1, Seattle
Manufacturing M2, Boston Manufacturing
13. Select File/Save.
14. Close Master items form by pressing F4
key.
Verifications:
1. Master Item form is displayed when
Navigate: Inventory/Items/Master Items.
2. Main Tab Region is displayed when enter
data to the Tab Regions.
3. Inventory Tab Region is displayed when
enter data to the Tab Regions.
4. MPS/MRP Tab Region is displayed when
enter data to the Tab Regions.
5. Work In Process Tab Region is displayed
when enter data to the Tab Regions.
6. Order Management Tab Region is
displayed when enter data to the Tab Regions.
7. Enable new item in M1 ,M2 when click
Assigned check box.
8. Organization Assignment form is
displayed Select File/Save
9. All of Master Items forms close and
focus returns to Navigator when press F4.
Responsibility:
Manufacturing & Distribution Manager Organization=M1, Seattle Manufacturing
(NOTE:
Specific Items used in this test refer to Vision seeded data.)
Task:
Define a discrete item
Actions:
1. Navigate: Inventory/Items/Master Items
2. Select Tools/Copy From. Item: CM13139
3. Click Apply.
4. Click Done.
5. Key in Item: ITEMTEST4,
Description:
Discrete Test Item
6. Verify Inventory Tab Region: Inventory
Item: Check Stockable: Check Reservable: Check Transactable: Check
Lot
- Control: No
Serial
- Generation: No Control
Locator
Control: No Control
7. Enter data for:
General
Planning Tab Region:
Inventory
Planning Method: Re-Order Point
Make
or Buy: Buy
Order
Quantity: Minimum: 5
Cost:
Order: 5
Cost:
Carrying: 10%
Source:
Type: Supplier
Safety
Stock: Method: Non MRP Planned
Safety
Stock : Percent: 15
8. Enter data for:
MPS/MRP
Planning Tab Region: Planning Method: MPS planning Forecast Control: Consume
and Derive Pegging: None
MPS
Planning: Calculate ATP: Check
MPS
Planning: Reduce MPS:None
Planning
Time Fence: User-Defined, Days: 8
Demand
Time Fence: User-Defined, Days: 3
9. Verify Work In Process Tab Region:
Build in WIP: Check
Supply
- type: Operation Pull
10. Select File/Save (stay in form for next
step)
11. Select Tools/Organization Assignment
12. Click Assigned check box for:
M1,
Seattle Manufacturing
M2,
Boston Manufacturing
13. Select File/Save.
14. Close Master items form by pressing F4
key.
Verifications:
1. Master Item form is displayed when
Navigate: Inventory/Items/Master Items.
2. Inventory Tab Region is displayed when
enter data to the Tab Regions.
3. General Planning Tab Region is
displayed when enter data to the Tab Regions.
4. MPS/MRP Tab Region is displayed when
enter data to the Tab Regions.
5. Work In Process Tab Region is displayed
when enter data to the Tab Regions.
6. Enable new item in M1, M2 when click
Assigned check box.
7. Organization form is displayed when
Select File/Save.
8. All of Master Items forms close and
focus returns to Navigator when press F4.
Script: MisTrans -
Miscellaneous Transaction
Responsibility:
Manufacturing & Distribution Manager Organization=M1, Seattle Manufacturing
(NOTE:
Specific Items used in this test refer to Vision seeded data.)
Task:
Perform Miscellaneous Transactions
Responsibility:
Manufacturing & Distribution Manager Organization=M1, Seattle Manufacturing
(NOTE:
Specific Items used in this test refer to Vision seeded data.)
Actions:
1.
Navigate: Inventory/Transactions/Miscellaneous Transaction.
2. Enter Transaction Type: Type:
Miscellaneous Receipt
3. Enter Transaction Source: Source: blank
4. Click Transaction Lines.
5. Enter Line information for first item:
Item: ITEMTEST1 Subinventory: Stores
UOM:
Each
Quantity:
30
6. Click on the List of Values icon for
the account field.
7. Enter “Miscellaneous” in the alias box.
8. Click OK.
9. Select File/Save
10. Enter Line information for second item:
Item: ITEMTEST2
Subinventory:
Stores
UOM:
Each
Quantity:
30
11. Click on the List of Values icon for the
account field.
12. Enter “Miscellaneous” in the alias box.
13. Click OK.
14. Select File/Save.
15. Select File/Close Form to close form.
Verifications:
1. Miscellaneous Transaction form is
displayed when Navigate: Inventory/Transactions/Miscellaneous Transaction.
Note:
Make sure the Inventory accounting periods that you are transacting in are open
2. Miscellaneous Transaction form is
displayed when enter Transaction Source.
3. Miscellaneous receipt form is displayed
when click the the Transaction Lines button.
4. Miscellaneous receipt form is displayed
when enter Line information. Alias look up box results.
5. Miscellaneous receipt form is displayed
when enter Line information.
6. All Miscellaneous Transaction forms
close and focus returns to Navigator when select File/Close Form.
Task:
Perform Sub-Inventory Transfer to move Responsibility: Manufacturing &
Distribution Manager Organization=M1, Seattle Manufacturing
(NOTE:
Specific Items used in this test refer to Vision seeded data.)
Task:
Perform Sub-Inventory Transfer to move
Actions:
1. Navigate:
Inventory/Transactions/Subinventory Transfer
2. Enter Transaction Type: Type:
Subinventory Transfer
3. Click Transaction Lines.
4. Enter Line Information Item: ITEMTEST2
Subinventory: Stores To Subinventory: MRB
UOM:
Each
Quantity:
10
5. Select File/Save
6. Selecting File/Close Form to close
form.
Verifications:
1. Subinventory transfer form is displayed
when Navigate: Inventory/Transactions/ Subinventory Transfer.
Note:
Make sure the Inventory accounting periods that you are transacting in are open
2. Inventory sub transfer form is
displayed when click Transaction Lines button.
3. All Subinventory Transfer forms close
and focus returns to Navigator when Select File/Close Form.
Responsibility:
Manufacturing & Distribution Manager
(NOTE:
Specific Items used in this test refer to Vision seeded data.)
Task:
Verify Shipping Network
Actions:
1. Navigate:
Inventory/Setup/Organizations/Shipping Networks
M1,
Seattle Manufacturing should show as the default organization when the form
opens.
2. Click Find.
3. Verify that From M1 to M2 exists and
that the Transfer Type equals Direct. Note: If Transfer Type is Intransit
change to Direct and save the record
4. Select File/Close Form to close form.
Verifications:
Shipping
Networks form is displayed when Navigate:
Inventory/Setup/Organizations/Shipping Networks.
Shipping
Networks form is displayed when Click the Find button.
Shipping
Networks form closes and focus returns to Navigator when select File/Close
Form.
Responsibility:
Manufacturing & Distribution Manager Organization=M1, Seattle Manufacturing
(NOTE:
Specific Items used in this test refer to Vision seeded data.)
Task:
Perform Inter-Org Transfer
Actions:
1. Navigate:
Inventory/Transactions/Inter-Organization Transfer
2. Enter Header Information:
To
Org: Boston Manufacturing, M2
Type:
Inventory direct org transfer or Inventory in transit shipment
3. Click Transaction Lines.
4. Answer yes if a folder decision box is
presented.
5. Enter Line Information: Item: ITEMTEST1
Subinventory: Stores To Subinventory: Stores UOM: Each Quantity: 5
6. Select File/Save
7. Select File/Close Form to Close form.
Verifications:
1. Inter-org Transfer form is displayed
when Navigate: Inventory/Transactions/Inter-Organization Transfer.
Note:
Make sure the Inventory accounting periods that you are transacting in are open
2. Inventory intransit shipment form is
displayed when click Transaction Lines button.
3. All
Inter-Organization Transfer forms close and focus returns to Navigator when
select File/Close Form.
No comments:
Post a Comment