To understand Payroll
Costing concept, I would first discuss the Costing Allocation Key Flex field,
during the business group definition it is being created and map with Cost
Allocation KFF with following segments normally
This setting will explain that the Natural Account information will be input at following levels
Now based on the above configuration the Cost Breakdown report will be shown like this
• Company
• Cost Centre
• Natural Account
• Cost Centre
• Natural Account
During the configuration
of Cost Allocation KFF the most important concept is to set the Flex Field
Qualifiers at each segment level, we have the five levels available for each
segment i.e.
• Payroll
• Balancing
• Organization
• Element Link
• Assignment
• Element Entry
• Balancing
• Organization
• Element Link
• Assignment
• Element Entry
For the Company segment
following setting can be applied
Payroll Checked
Balancing Checked
Balancing Checked
This setting will
explain that the Company Account will be input at Payroll level (debit
information) and balancing information will goes into credit information and on
every segment level it is mandatory to define Balancing.
For the Cost Centre
segment, I can set the following setting
Payroll Checked
Organization checked
Balancing checked
Organization checked
Balancing checked
This setting will explain
that the Cost Centre Account information will be input at Payroll and
Organization level (debit information) and balancing information will goes into
credit information and on every segment level it is mandatory to define
Balancing.
For the Natural Account
segment, I can choose the following setting
Element Link Checked
Assignment Checked
Element Entry Checked
Balancing Checked
Assignment Checked
Element Entry Checked
Balancing Checked
This setting will explain that the Natural Account information will be input at following levels
Element Link
Assignment
Element Entry
Balancing
Assignment
Element Entry
Balancing
Element Link,
Assignment, Element Entry level information will directly hit the debit account
and balancing information will goes into credit Account and on every segment
level it is mandatory to define Balancing.
After this step we map Cost
Allocation KFF Segments with GL Flex field Segments
In Oracle payroll,
Costing information can be input at five levels
• Payroll
• Organization
• Element Link
• Assignment
• Element Entry
• Organization
• Element Link
• Assignment
• Element Entry
Now based on the above
configuration, the following codes will be define at Payroll level
Company 01
Cost Centre 000
Cost Centre 000
For example if Business
Group has four Departments i.e. Finance, HR, IT, Operations then on every
organization the following information will be define at the Organization level
Finance Cost Centre 001
HR Cost Centre 002
IT Cost Centre 003
Operations Cost Centre 004
HR Cost Centre 002
IT Cost Centre 003
Operations Cost Centre 004
Note: Here the Cost
Centre information will override with information available on Payroll Level
Payroll Level 000
Finance Org Level 001
Finance Org Level 001
So the system will pick
the value of 001 instead of 000.
Finally following
information need to define at every Element Link level, for example if Business
Group has only three elements links then Natural Account need to define at
every link
Basic Salary 2345
Housing Allowance 2346
Transport Allowance 2347
Housing Allowance 2346
Transport Allowance 2347
For Assignment and
Element Entry levels, the Natural Accounts codes will not be defined at these
levels , but if need to override the link level information then the Natural
Account can be enter at assignment or Entry Level. Following the is Override
information, if we defined all segment on every level then
The following Entry will
be hit to GL
Debit 04.003.2222
Credit 01.000.6766
Credit 01.000.6766
Because Element Entry
Level will override all the above mention levels but this is only for example,
if we see this table in our scenario then the value will be shown like this
In this case the
following Entry will hit to GL accounts
Debit 01.001.2222
Credit 01.000.6766
Credit 01.000.6766
Now based on the above configuration the Cost Breakdown report will be shown like this
Cost Summary Breakdown
Report– Cost Centre wide
Cost Centre Code Cost
Centre Amount
001 Finance xxxx
002 HR xxxx
003 IT xxxx
004 Operation xxxx
Total xxxx.xx
001 Finance xxxx
002 HR xxxx
003 IT xxxx
004 Operation xxxx
Total xxxx.xx
Cost Breakdown Report–
Element wide.